| “This project gave us an opportunity to                                                  showcase our equipment”
|  |  | 
| Rakesh Kaul |  
| says Rakesh Kaul, General Manager, Elcome Technologies |  
| Pvt. Ltd., with reference to the survey equipment that they |  
| supplied for the Bandra-Worli Sea Link. |  |  
|  |  |  |  When did Elcome Technologies first get associated with HCC on the Bandra- Worli Sea Link Project? Leica equipment has been used on most of the Sea Link projects around the world and based on this experience we approached Hindustan Construction Company (HCC) sometime at the end of 2000 with our range of specialised equipments for the Bandra-Worli Sea Link (BWSL). The first Leica Total Station was supplied by us to HCC in early 2001.  What were the equipment supplied for this project? To meet the demand for high accuracy coordinate measurements on the BWSL project we supplied high performance Leica Total Stations including the TCA 2003, the TCA 1800, the TCA 1201, the TCRM 1201 R 300 and the TC 1800. We also supplied the SR 510 GPS equipment. What kind of support did you provide HCC vis-à-vis the equipment that you supplied to them? We gave comprehensive application trainings at their site towards effective and optimal usage of the equipment. Moreover, these equipments in keeping the desired accuracies that are required for such a project, needed timely calibration checks and corrections – for this, besides providing them complete service support during the warranty, we also got into annual maintenance  contracts for these equipment post their warranty period. We were thus able to provide timely service and calibration of the equipment at our service centre. Do you think being associated with the project gives Elcome Technologies any leverage for other similar projects? It has been a privilege to be associated with BWSL and the HCC team we worked with. Moreover the challenges in geometric control on the project were highly demanding and exacting. This gave us an opportunity to showcase our equipment and our expertise. Our experience with BWSL project will be a basis for us to promote our technology on other such projects too.   
Partners involved 1. VSL Singapore Pvt Ltd : Technical Consultants2. Ultra Tech : Supplier of cement
 3. Metco group of companies: Supplier of bearings
 4. Tata Steel, RIN Ltd & SAIL: Supplier of steel
 5. ELKEM International Ltd.: Norway-based company supplier of micro silica
 6. SPCC: China-based company supplier of stay cable
 7. DOKA Australia: supplier of Plyon fromwork
 Equipment used
 The major equipments deployed for this project are:
 • Jack up platform, launching truss, reverse circulation drilling machine floating barrages,                                              boats, crawler crane, tower crane, gantry crane, derrick crane, placer boom, diesel                                              generators, concrete pump, transit mixers & ‘A’ frame barrage.
 • The equipment was brought together from various countries.
 The construction of the mammoth bridge structure required huge cranes  and other structures to lift material for off shore and on shore  structures. Some of these included:
 1. Launching Truss: Weighing 1250 tonnes and measuring 112 m in length,  it was used for lifting segments each weighing 130 tonnes. This has  been fabricated in India.
 2. Jack up platform: Size 18.3x30x2.1m (Width x Length x Depth) having four legs of                                              30m. It is a floating equipment used for marine work.
 3. Flat barge: Size 30x12x2m. Like motor boats, they are driven inside  the sea for material transportation.
 4.  Self-propelled barge: It is a barge with a machine component and is  used for concrete transportation.
 5. Crawler crane: Capacity ranges from 75-150 tons. It is used for material and heavy                                              lifting activities.
 6. RCD drill bit: Dimension 1.5m x 2m diameter. Imported from Korea, the RCD drill bit                                              is used for pile drilling work.
 7. Vibro hammer (PTC): Imported from France and used for driving of steel liners.
 8. Fushun crawler crane: Imported from China, Capacity 80 tons.
 9. NCK Eiger crane: Imported from England, capacity 65 tons.
 10. Kobelco crawler crane: Imported from Hong Kong, capacity 150 tons. Fascinating facts • The project has already been acclaimed by the viewers as an engineering marvel of                                              modern India.
 • First Cable-Stay Bridge in India in open sea.
 • The length of the bridge is 63 times the height of the Qutub Minar in Delhi.
 • Its weight is equivalent to 50,000 African elephants.
 • The length of the steel wires used is equivalent to the circumference of the earth.
 • The height of the cable-stayed tower is 128 m, which is equal to a 43-storey building.
 • A total of 424 cables were used for both Bandra cable stay as well as Worli cable stay                                              bridges.
 • The cables have been sourced from Shanghai Pujyang Cable Company,  China. The cables were subject to a series of quality and engineering  tests to meet the special requirements including fatigue tests of two  million cycles.
 • The cables are made of high tensile steel and are designed to take the maximum load of                                              900 tons.
 • 92,000 tons of cement was utilized to make BWSL.
 • Environment friendliness was top priority during the construction – fly ash, a waste                                              product extracted from thermal power plants, was mixed with concrete, to make the                                              construction durable as well as eco-friendly, thus making good use of waste material.
 • The construction team is like a mini United Nations: several teams of foreign engineers                                              and technicians have worked on specialized tasks on the structure; these include                                              professionals from China, Egypt, Canada, Switzerland, Britain, Serbia, Singapore,                                              Thailand, Hong Kong, Indonesia and the Philippines, Australia.
 • The Launching Trusses, each 112 meters long, were custom built to  precision by HCC for this project. The pre-cast concrete segments of  this four-lane road are fabricated at the Bandra site location. These  segments are then carried on a barge to the construction location and  are lifted by the Launching Truss to the designated height and  assembled between two piers, each 50 meters apart. Fifteen such  segments are fitted between two piers and the Launching Truss can lift  all fifteen segments together, weighing 130 tons each, between two  piers. Once these segments are fixed between two piers, the Launching
 Truss crawls to the next piers on its mechanical legs.
 • Given the gigantic size of the project, mega equipments were used in  construction; bringing them to the project site and operating them was  a feat in itself. Asian Hercules, one of the biggest floating shear leg  cranes in the world, was hired from Singapore to lift the massive 1250  tonnes, custom-built Launching Trusses with its mechanical arm and  relocate them on the Worli side of the bridge.
 Hindustan Construction Company (HCC)
 1. VSL Singapore Pvt Ltd : Technical Consultants
 2. Ultra Tech : Supplier of cement
 3. Metco group of companies: Supplier of bearings
 4. Tata Steel, RIN Ltd & SAIL: Supplier of steel
 5. ELKEM International Ltd.: Norway-based company supplier of micro silica
 6. SPCC: China-based company supplier of stay cable
 7. DOKA Australia: supplier of Plyon fromwork Equipment used The major equipments deployed for this project are:
 • Jack up platform, launching truss, reverse circulation drilling machine floating barrages,                                              boats, crawler crane, tower crane, gantry crane, derrick crane, placer boom, diesel                                              generators, concrete pump, transit mixers & ‘A’ frame barrage.
 • The equipment was brought together from various countries.
 The construction of the mammoth bridge structure required huge cranes  and other structures to lift material for off shore and on shore  structures. Some of these included:
 1. Launching Truss: Weighing 1250 tonnes and measuring 112 m in length,  it was used for lifting segments each weighing 130 tonnes. This has  been fabricated in India.
 2. Jack up platform: Size 18.3x30x2.1m (Width x Length x Depth) having four legs of                                              30m. It is a floating equipment used for marine work.
 3. Flat barge: Size 30x12x2m. Like motor boats, they are driven inside  the sea for material transportation.
 4.  Self-propelled barge: It is a barge with a machine component and is  used for concrete transportation.
 5. Crawler crane: Capacity ranges from 75-150 tons. It is used for material and heavy                                              lifting activities.
 6. RCD drill bit: Dimension 1.5m x 2m diameter. Imported from Korea, the RCD drill bit                                              is used for pile drilling work.
 7. Vibro hammer (PTC): Imported from France and used for driving of steel liners.
 8. Fushun crawler crane: Imported from China, Capacity 80 tons.
 9. NCK Eiger crane: Imported from England, capacity 65 tons.
 10. Kobelco crawler crane: Imported from Hong Kong, capacity 150 tons. Fascinating facts • The project has already been acclaimed by the viewers as an engineering marvel of                                              modern India.
 • First Cable-Stay Bridge in India in open sea.
 • The length of the bridge is 63 times the height of the Qutub Minar in Delhi.
 • Its weight is equivalent to 50,000 African elephants.
 • The length of the steel wires used is equivalent to the circumference of the earth.
 • The height of the cable-stayed tower is 128 m, which is equal to a 43-storey building.
 • A total of 424 cables were used for both Bandra cable stay as well as Worli cable stay                                              bridges.
 • The cables have been sourced from Shanghai Pujyang Cable Company, China. The cables
 were subject to a series of quality and engineering tests to meet the  special requirements including fatigue tests of two million cycles.
 • The cables are made of high tensile steel and are designed to take the maximum load of                                              900 tons.
 • 92,000 tons of cement was utilized to make BWSL.
 • Environment friendliness was top priority during the construction – fly ash, a waste                                              product extracted from thermal power plants, was mixed with concrete, to make the                                              construction durable as well as eco-friendly, thus making good use of waste material.
 • The construction team is like a mini United Nations: several teams of foreign engineers                                              and technicians have worked on specialized tasks on the structure; these include                                              professionals from China, Egypt, Canada, Switzerland, Britain, Serbia, Singapore,                                              Thailand, Hong Kong, Indonesia and the Philippines, Australia.
 • The Launching Trusses, each 112 meters long, were custom built to  precision by HCC for this project. The pre-cast concrete segments of  this four-lane road are fabricated at the Bandra site location. These  segments are then carried on a barge to the construction location and  are lifted by the Launching Truss to the designated height and  assembled between two piers, each 50 meters apart. Fifteen such  segments are fitted between two piers and the Launching Truss can lift  all fifteen segments together, weighing 130 tons each, between two  piers. Once these segments are fixed between two piers, the Launching
 Truss crawls to the next piers on its mechanical legs.
 • Given the gigantic size of the project, mega equipments were used in construction;
 bringing them to the project site and operating them was a feat in  itself. Asian Hercules, one of the biggest floating shear leg cranes in  the world, was hired from Singapore to lift the massive 1250 tonnes,  custom-built Launching Trusses with its mechanical arm and relocate  them on the Worli side of the bridge. Hindustan Construction Company (HCC).
 | 
Hi
I think this project is a part of the Western Freeway Sea Project, which, in turn, is a part of a larger proposal to upgrade the road transportation network of greater Mumbai.
GPS could play a great role in construction control.
Leave your response!
MY NEWS
- Dr. Jason Anderson receives Parkinson award 
- Logan Scott receives Kepler award 
- ESA’s Celeste LEO-PNT demonstrator mission set to launch in December 
- E-GIANTS project concludes study on GNSS authentication and security improvements 
- Verra releases innovative digital soil mapping tool 
More...Order both the copies for FREE!
PREVIEW THE BOOK
PREVIEW THE BOOK
________________________________________
The Drone Rules in India 2021
________________________________________
National Geospatial Policy of India 2022
________________________________________
Indian Satellite Navigation Policy – 2021 (Draft)
________________________________________
Guidelines for acquiring and producing Geospatial Data and Geospatial Data Services including Maps
________________________________________
Draft Space Based Remote Sensing Policy of India – 2020
________________________________________
National Unmanned Aircraft System (UAS) Traffic Management Policy – Draft
________________________________________
Advertisement
Interview
Kiyokazu Minami
Secretary General, Executive Director, Japan Institute of Navigation
Member, Leader of GPS/GNSS research group, Japan Institute of Navigation
Easy Subscribe
Previous Issues
- Vol. XXI, Issue 5, May 2025
- Vol. XXI, Issue 4, April 2025
- Vol. XXI, Issue 3, March 2025
- Vol. XXI, Issue 2, February 2025
- Vol. XXI, Issue 1, January 2025
- Vol. XX, Issue 12, December 2024
- Vol. XX, Issue 11, November 2024
- Vol. XX, Issue 10, October 2024
- Vol. XX, Issue 9, September 2024
- Vol. XX, Issue 8, August 2024
- Vol. XX, Issue 7, July 2024
- Vol. XX, Issue 6, June 2024
- Vol. XX, Issue 5, May 2024
- Vol. XX, Issue 4, April 2024
- Vol. XX, Issue 3, March 2024
View AllLog In
E-ZINE
- April 2025
- March 2025
- February 2025
- January 2025
- December 2024
- November 2024
- October 2024
- September 2024
- August 2024
- July 2024
- June 2024
- May 2024
View AllPartnership
10 - 12 February, 2025
The Queen Elizabeth II Centre, London
1-3 April
Porto, Portugal
9-10 April 2025
Singapore
23-24 April 2025
Washington DC, USA
5 - 6 May 2025
Jeddah, Saudi Arabia.
12-14, May
Ottawa, Canada
21-23, May 2025
Wrocław, Poland
4 - 5 June
London, UK
8-12 September
Baltimore, USA
17-18 September
Hyderabad, India
21 - 24 September 2025
Baška, Krk Island, Croatia
29–30 October 2025
Riyadh, Saudi Arabia.
3-5,November
Calgary, Canada
3-5 November 2025
Florianópolis, Santa Catarina, Brazil
28 – 30 April 2026
Vienna, Austria
21-23 May
Benidorm, Spain
View Past Events